| Workpiece |
| Category |
General Machine component |
|
| Name |
Hydraulic component |
| Material |
SUS |
| Description |
Primary hole 20mm dia. Secondary hole 5.3mm dia. |
| Pre-Processing |
Drilling |
| Processing Methods/Conditions |
| Tool Used |
CH-PM-5B |
|
| Description |
After drilling, contour the bore edge to remove burrs |
| Conditions |
Tool Revolutions 5000rpm |
| Depth of Cut 0.5mm |
| Feed Rate 300mm/min |
| Effectiveness on Installation of XEBEC Cross-Hole Deburring Tool |
| Before |
Tool Used:Cutter |
|
| Manual processing with a cutter resulted in inefficiency and unstable finishing
quality |
| After |
Tool Used:Cross-Hole Deburring Tool Ceramic Stone Type CH-PM-5B |
|
| Full automation with marching centers was possible and quality became stable |